Electricity Is Essential For Dignified Living; Restoring Supply Does Not Give Occupants Property Rights: Calcutta High Court

Electricity Is Essential For Dignified Living; Restoring Supply Does Not Give Occupants Property Rights: Calcutta High Court

2026 (0) AIJEL-WB 547829

In a significant ruling, the Calcutta High Court has upheld the restoration of electricity supply to occupants of a property, despite ongoing disputes regarding the premises' condition and the authority of the Kolkata Municipal Corporation (KMC). The appeal, MAT 1386 of 2026, was filed against an order dated August 6, 2026, which directed the CESC (Calcutta Electric Supply Corporation) to restore electric supply to the writ petitioners, who had previously experienced disconnection due to safety hazards caused by water percolation at the meter board location.

The court noted that the disconnection was a necessary precaution to prevent potential fire hazards and electrification risks. The learned Single Judge had ordered that upon the petitioners' application for reconnection, CESC must provide a quotation for costs, which, once deposited, would lead to the removal of the existing service cable and allow for repairs to the dilapidated meter board. The court mandated that these repairs be completed within three days of the deposit.

During the appeal, the appellants, represented by Mr. Aniruddha Chatterjee, argued that the order adversely affected the landlords' rights and contradicted prior orders from the KMC under Section 412A of the Kolkata Municipal Corporation Act, 1980. They contended that the premises were in a dilapidated state, and allowing electricity supply would imply an acknowledgment of the occupants' rights to remain in the property.

Conversely, the writ petitioners, represented by Mr. Biswaroop Bhattacharya, maintained that the challenge to the KMC's proceedings was still pending and that the matters should be adjudicated on their own merits without affecting the restoration of electricity.

The court, after considering the arguments, emphasized the essential nature of electricity as a commodity vital for a dignified life. It ruled that the restoration of electricity should not create any rights or equities in favor of the occupants, as their status remains undecided in this proceeding. The court clarified that the restoration is subject to any ongoing proceedings initiated by the KMC or pending in civil court.

Ultimately, the appeal was disposed of without any order as to costs, reinforcing the principle that access to electricity is integral to modern living and should not be denied without just cause.